COMPANY |
OBJECT |
EQUIPMENT |
JSC Yamal LNG |
Fuel and lubricant upper warehouse |
2APTS-1000 kVA |
Construction of a complex for the extraction, preparation, liquefaction of gas, shipment of LNG and gas condensate of South-Tambey Gas condensate field. A workshop for processing Construction of a complex for the extraction, preparation, liquefaction of gas, shipment of LNG and gas condensate South-Tambey Gas condensate field. A workshop for processing of drilling slurry |
Modular 2APTS-2000С/6/0,4kV |
Yuzhno-Tambeyskoye gas field |
2PTS-2500, 2PTS -1000, LV DBs |
LNG PLANT. Inlet facilities |
3APTS-1600(250) С/10/0,4 kV
3APTS-1000(250) С/10/0,4 kV
3APTS-1600(250) С/10/0,4 kV
3APTS-1000(250) С/10/0,4 kV |
LNG PLANT. Auxiliary facilities. Water purification plant. Water supply pump station |
2APTS-2500С/10/0,4 kV, UPS System 10 kVА |
LNG PLANT. Auxiliary facilities. Fire-water supply pumping station. Pumping station |
Indoor Distribution Device -10 kV of 19 cubicles 2PTS-1000С/10/0,4 kV
UPS System 10 kVА
HV soft start system, Uin=10 kV, Uout=10kV
UPS System DC = 110V |
LNG PLANT. Inlet facilities for gas treatment. Utilities. Electric power grids |
2PTS-1600С/10/0,4 kV
UPS System 10 kVА |
Facility 33-J02-00. Sea port. Sea port main facilities. Technological port terminal N 2. |
Distribution transformer substation №1 |
Facility 40-0180-41. Sea port. Port terminal N 1 back area buildings and constructions. |
Transformer house 2 PTS (С)-1250/10/0,4 HL1 |
LNG PLANT. Auxiliary facilities. Waste water treatment plants. Pump station |
Transformer substation complete with:
-
Packaged Switchgear 10kV consisting of 19 cubicles;
-
Two-transformer substation with two LV cabinets 2PTS -2000С/10/0,4 kV;
-
HV System of Soft start, Uin=10 kV, Uout=10kV;
-
HV System of variable frequency drive Uin=10 kV, Uout=10kV;
-
UPS System 10 kVА, Uin=400V, Uout=400V;
-
UPS System DC = 110V
|
MULTIPLE-WELL PLATFORMS, well cluster, 1, 2, 46, 25, 43, 44, 47, 155-Р |
Power supply packaged modular device 0,4 kV
UPS System 60 kVА |
LNG PLANT. Temporary work camp for builders of EPC contractor |
Transformer substation 6/0,4 kV 630kVА |
LNG PLANT. Auxiliary facilities. Out-of-site networks |
Heat tracing electric supply enclosure |
LNG PLANT. Stable condensate storage tanks |
3APTS-1000(250)С/10/0,4 kV; UPS System 6,6 МW, Uin=10kV, Uout=10kV; Soft start thyristor panels ; UPS System 20 kVА; UPS System 15 kVА; UPS System 10 kVА |
LNG PLANT. Gas treatment unit. |
Heat tracing panels |
LNGC with capacity up to 1 mln tons of LNG per year in Sabetta village |
LV DBs, PTS 10/0.4, packaged switchgear -10 kV, UPS systems in modular building with fire protection system, including fire extinguishing system and ventilation |
33-7010-01. Natural gas liquefaction complex with capacity up to 1 mln tons of LNG per year in Sabetta. Gas liquefaction unit (LNG). On-site networks. Power supply grids |
Uninterruptible power supply system 545- UP019-F01 |
31-0330-01. Expansion of gas collection system and inlet facilities at the Yuzhno-Tambeyskoye gas field. Gas treatment unit (GTU). Compression unit. Power unit |
Uninterruptible power supply system 545- UP019-V01 with low voltage switchboard 545- DB019-V01 |
33-7000-11. Natural gas liquefaction complex. Outdoor unit. Transformer substation |
Uninterruptible power supply system 445- UP048-V01 with low voltage switchboard 445- DB048-V01 |
31-4010-01. Natural gas liquefaction complex with capacity up to 1 mln tons of LNG per year in Sabetta. Gas treatment unit (GTU). On-site grids. Power supply grids |
Uninterruptible power supply system 445-UP048-V01 with LV DB 445-DB048-V01 |
33-7010-01. Natural gas liquefaction complex with capacity up to 1 mln tons of LNG per year in Sabetta. Gas liquefaction unit (GLU). On-site grids. Power supply grids |
UPS system 445-UP048-F01 |
33-7010-11. Natural gas liquefaction complex with capacity up to 1 mln tons of LNG per year in Sabetta. Gas liquefaction unit (GLU). Transformer substation |
Modular building ESS-047 |
31-4010-01. Natural gas liquefaction complex with capacity up to 1 mln tons of LNG per year in Sabetta. Gas treatment unit (GTU). On-site grids. Power supply grids |
PTS ESS-019 |
OOO ARCTIC LNG2 |
Development of Salmanovsky (Utrenee) OGCF |
Power supply container unit |
Rotators' camp, fuel and lubricant depot, administration zone, sewage pumping station, waste water treatment station |
PTS 10/0.4, modular-packaged electrical power plant with DGU 150 kW, LV DBs, packaged switchgear -10 kV in modular building with auxiliaries. |
Construction of the Salmanovskoye (Utrenneye) OGCF. Gas supply of power supply facilities for construction needs, hydrotreatment and drilling |
Packaged transformer substation - 15 sets. |
Construction of the Salmanovskoye (Utrenneye) oil and gas condensate field. Industrial and fire-fighting water supply facilities |
Step-down substation with 0.4 kV switchgear pos. ESS-827 |
Construction of Salmanovskoye (Utrenneye) OGCF. Gas supply of power supply facilities for construction needs, hydrotreatment and drilling. Cluster of gas condensate wells No.2 |
ESS-608 module of power supply |
Construction of the Salmanovskoye (Utrenneye) OGCF. Gas supply of power supply facilities for construction needs, hydrotreatment and drilling. Water intake-2. |
Module of power supply ESS-704 |
Salmanovskoye (Utrenneye) OGCF development. Gas supply of the power supply facilities for the construction needs, soil jetting and drilling. Temporary camp for the builders of the LNG plant and SGC at GTU |
Transformer substation 10/0.4 kV N10.4 |
Construction of the Salmanovskoye (Utrenneye) OGCF. Gas supply of power supply facilities for construction needs, hydrotreatment and drilling. Gas turbine power plant |
Building of indoor switchgear with packaged switchgears 35, 10 kV GTPP |
Prefabrication of Salmanovskoye (Utrenneye) OGCF. Off-site grids. Electric heating grids. |
Package transformer substation of heating system -12 pcs. |
OOO Cryogas-Vysotsk Vysotsk LNG |
Cryogas-Vysotsk Vysotsk LNG |
10kV switchgear-10 pcs,
LV switchgear -10 pcs, Packaged transformer substation - 8 pcs,
LV switchgear for gas air cooling unit - 4 pcs,
Operating DC voltage system,
UPS, ACS |