OJSC SEVERNEFTEGAZPROM

ja_mageia

Block-modular buildings

Our block-modular buildings
are characterized by presence of
additional anticorrosion treatment
as applied to certain maintenance conditions.

  • Decrease font size
  • Default font size
  • Increase font size
CHETA LLC The company Major projects OJSC SEVERNEFTEGAZPROM
OJSC SEVERNEFTEGAZPROM Print

(Supply of equipment for the project «Yuzhno-Russkoye field development. Installation of LNG processing equipment»).

Design organization: PAO Yuzhniigiprogaz, Donetsk

Contract signing date: December 2006

Delivery expectancy: 31.04.2007

Actual delivery: March – April, 2007

Scope of supply:

  • MCC panels with withdrawable units for water supply compressor station, methanol and regenerates compressor station, Tri Ethylene Glycol regeneration unit, first and second gas drying units, switching valves and gas metering buildings, sewage treatment facility buildings and pumping building of deep layer injection.
  • Packaged transformer substations 2PTSA-1000/10/10/0.4 kV for power supply building, water supply compressor and Tri Ethylene Glycol regeneration unit.

Equipment information:

MCC panels with withdrawable units, packaged transformer substations were designed on the base of SIVACON panels with Siemens equipment by design organization PAO Yuzhniyigiprogaz, Donetsk.

CHETA LLC in the competitive struggle against foreign companies won a tender for he supply of MCC panels and packaged transformer substations with withdrawable units for the facility "Construction of the Yuzhno-Russkoye field".

During the manufacturing process CHETA LLC has developed and agreed with design organization PAO Yuzhniigiprogaz, and Customer OJSC Severneftegazprom design documentation for manufacturing of MCC panels with withdrawable units and packaged transformer substations.

MCC panels were manufactured by CHETA LLC in its own design MV 4000. Packaged transformer substations - of CHETA’s design with General Electric circuit breakers, ATS was implemented on the base of industrial controller device and connection between the PTS and APCMS was performed via optical cable.

Start-up operations:

The contractor performed the full scope of installation and commissioning works. Commissioning works were carried out by CHETA. There were no claims about the quality of products in the process of performance of works from the contractor organization and from the Customer.

6 months have passed from the date of delivery of the main equipment until commissioning of facilities. This was facilitated by high technical level of MCC panels and PTS with all kinds of adjustments and tests at the manufacturing plant that allowed to make installation and commissioning of MCC panels and PTS with no load and under load in the shortest time. The ceremony of commissioning of Yuzhno-Russkoye field was held in October 2007 in the presence of the First Deputy Chairman of the Government of the Russian Federation, Chairman of the Board of Directors of PJSC Gazprom Dmitry Medvedev and Vice-Chancellor, German Foreign Minister Frank- Walter Steinmeier.

In total the following production was supplied:

At the end of 2008 industrial packaged transformer substations 2PTS-1600/10/0.4 kVA, 2PTS-1600N/10/0.4 kVA with emergency power supply, MCC panels with withdrawable units for the power unit of the Booster Compressor Shop No. 1 were supplied. In 2009 the full scope of installation and commissioning works was performed by the contracting company. In October 2010 the first stage of the Booster Compressor Shop No. 1 of the compressor station was put into operation. Within the frame of project "Construction of the Yuzhno-Russkoye oil and gas field. GTU. Booster Compressor Shop No. 1 (Second Stage)" the following production was supplied:

  • industrial packaged transformer substations 2PTS-1600/10/0.4 kVA, 2PTS- 1600N/10/0,4 kVA, MCC panels with withdrawable units for power plant;
  • modular packaged transformer substations 2PTS-1000/10/0.4-UHL1, 2 for «Shift teams meeting point in Novy Urengoy»; 2PTS-400/10/0.4 for «Field camp», 2BPTS-6C0/1 0/0.4 - UHL1 for «Prombaza»;
  • in the period from January 2015 until October 2015 complex of construction, installation and commissioning works for PTS, MCC and main technological equipment was performed by the contractor.

In December 25, 2015 the second stage of Booster Compressor Shop No. 1 of Yuzhno-Russkoye field was put into commercial operation.

Feedback:

in 2002 CHETA LLC has carried out the delivery of LV SWG and PTS, conducted the commissioning of the equipment for Yuzhno-Russkoye field OGCF of OJSC Severneftegazprom. The delivered equipment was manufactured at a high technical level and modern element base. System solutions applied provide reliable operation. In the course of joint work at the facilities of the field, high quality of equipment, timely fulfillment of contractual obligations and high level of technical specialists of CHETA LLC were noted.

General Director of OJSC Severneftegazprom - A.P. Popov

 
Russian (CIS)English (United Kingdom)

 

Reference list

Here you may familiarize yourself with our reference list

ja_mageia

  • Наверх