Крупные реализованные проекты

ja_mageia

Automated control system of gas-compressor unit

ACS GCU on the controllers
ControlLogix series of Allen Bradley
and Flexlogix (Rockwell Automation) base
includes smart panels of LVCD and supplied
integrated in block-modular building.

  • Decrease font size
  • Default font size
  • Increase font size
CHETA LLC The company Major projects
MAJOR IMPLEMENTED PROJECTS
LLP « ZHAIKMUNAI» PDF Print E-mail

(Equipment supply for the project «Electrical grid infrastructure modernization of Chinarevskoe oil/gas-condensate field»).

Design organization: LLP «Joint Enterprise « Soyuzkomplekt», Almaty

Contract signing date: 30.07.2014

Delivery expectancy: 31.12.2014

Actual delivery: November 2014

Scope of delivery:

  • Modular Packaged Switchgear 10 kV «Chinarevo-1» inside the block modular building with overall dimensions 34*9*3 with room for staff and control room.
  • Modular Packaged Switchgear 35 kV «Chinarevo-1» inside block modular building with overall dimensions (L*W*H) 29*6*3. Additional equipment – differential protection panel, differential bus protection panel, telecontrol panel , metering panel, general protection panel and automatic voltage control panel Т1 and Т2.
  • Modular Packaged Switchgear 35 kV «Burovie-1» and Modular Packaged Switchgear 35 kV «Burovie-2», joined together with metal clad switchgear 10 kV inside block modular buildings with overall dimensions 15,4*6*3. Additional equipment – on-load changing control panel, central alarm panel, telecontrol panel, metering panel.
  • Modular Packaged Switchgear 35 kV «UKPG» inside block modular building with overall dimensions 15*6*3, additional equipment - differential protection panel-35, differential bus protection panel -35.
  • Modular Packaged Switchgear 6 kV «UKPG» inside block modular building with overall dimensions 15*6*3, additional equipment – central alarm panel, differential protection panel -6, differential bus protection panel-6, automatic voltage control panel Т1, automatic voltage control panel Т2, telecontrol panel, metering panel.
  • LLP “ZHAIKMUNAI” Chinarevskoe oil/gas-condensate field automated system of electrical grid infrastructure technological supervision control of automated system (ASEGITCS).
Read more... [LLP « ZHAIKMUNAI»]
 
JSC «SEVERNEFTEGAZPROM» PDF Print E-mail

(Equipment supply for the project «Yuzhno-Russkoye field. Installation of LNG processing equipment»).

Design organization: PJSC Yuzhniyigiprogaz, Donetsk

Contract signing date: December 2006

Delivery expectancy: Delivery expectancy: 31.04.2007

Actual delivery: March – April, 2007

Scope of delivery:

  • PCB panels with withdrawable units for water supply compressor station, methanol and regenerates compressor station, first and second gas drying units, switching valves and gas metering buildings, sewage treatment facility buildings, building of compressor pumping sewage into the layer.
  • Complete transformer substations 2KTPA-1000-10-10/0,4 kV for power supply building, water supply compressor.
Read more... [JSC «SEVERNEFTEGAZPROM»]
 
OJSC «ARKTIKGAZ» PDF Print E-mail

(Equipment supply for the project "Arrangement of Valanginian reservoir of the Samburgskoye field for the period of test operation. Installation of LNG processing equipment).

Design organization: PJSC Yuzhniyigiprogaz, Donetsk

Contract signing date: September 2011

Delivery expectancy: 31.12.2011

Actual delivery: December, 2011

Scope of delivery:

  • Complete transformer substation 2KTPP-1600s-6/0,4-UЗ for gas and condensate processing unit.
  • Complete transformer substations KTPP-400С-6/0,4-UЗ, 2BKTPA-1600S-6/0,4 kV, 2BKTPP-1250S-6/0,4 kV, 2BKTPP- 1600S-6/0,4 kV for GPP.
  • LVCD panels with withdrawable units.
  • Automated capacitor units (ACU) for transformer substation.
  • ALT panels.
  • Control station panels with soft start panel.
  • Electric supply block-box of set-up transformer.
  • Hinged design power panels, lighting panels, power distributor cabinets, YaRP, Ya5111, YaVZ, YaOU9601.
Read more... [OJSC «ARKTIKGAZ»]
 
«YARGEO» LLC (NOVATEK) PDF Print E-mail

(Arrangement of Yarudeyskoye field).

Design organization: GIPRONG-ECOM, IPIgaz

Contract signing date: June 2013

Delivery expectancy: 31.07.2014

Actual delivery: July 2014

Scope of delivery:

  • Complete transformer substations with capacity from 63 up to 2500kVА for voltage 10/0,4 kV (22 pcs.).
  • Linear consumer blocks.
  • Block-boxes with LVCD.
Read more... [«YARGEO» LLC (NOVATEK)]
 
OJSC «KAZANORGSINTEZ» PDF Print E-mail

(Bisphenol A production plant)

Scope of delivery: Complete power transformer substations 2KTPP–1600 kVA,2KTPP–1000 kVA, MCC of withdrawable modules design.

Equipment information: «CHETA» LLC based on technical design assignment (engineered in cooperation with TOYO Engineering corporation) carried out a works on initial data movement to General Designer OAO «Samaraneftechimproekt». Also «CHETA» participated in development of work documentation. After equipment delivery in a very short time with the participation of «CHETA» engineers have been carried out pre-commissioning works and factory had been brought into operation in time (in 2007).

During operation period «CHETA» didn’t received any complaint.

 
«LUKOIL-NIZHEGORODNEFTEORGSINTEZ» LLC PDF Print E-mail

(Unit for production of elementary sulphur as part of combination hydrogen sulfide processing unit, unit of absorption and hydrocarbon gases declustering of hydrocarbon gases, atmospheric and vacuum crude unit, Distribution Transformer Substation.

Scope of delivery: Complete power transformer substations 2KTP–1000 kVA, 2KTP–1600 kVA, MCC panels.

Equipment information: LVCD’s and Double Packaged Transformer Substations were made based on «General Electric» equipment. Based on totality of product characteristics «CHETA» LLC won in the tender in competition with «Siemens».

 
JSC «YAMAL LNG» PDF Print E-mail

(Integrated development of South-Tambay Gas-Condensate field. Complex of preparation of gas liquefaction. Seaport, base camp, POL storage).

Scope of delivery: Complete power transformer substations 2BKTPA-2000С/6/0,4 kV, 2KTP–2500, 2KTP-1000, 2BKTPA-1000 kVA, MCC panels.

Equipment information: Double- and three-section transformer substation of voltage class 10/0,4 kV at 4b form in block-modular buildings based on “General Electric” equipment, UPS systems for power from 5 to 30 kVA with working time from 60 to 480 minutes, soft starter system with capacity of 6.6 mW with Solcon power unit at Dynex thyristors, 10kV switchgear based on VEP-12 breakers (consists of 10 RSN-10 compartments) as well as LVCD’s of withdrawable modules design. Also there were supplied 7 one-ended and double-ended mobile substations with capacity 630 kVA for base camp with provided universal cable entry. According to the customer request - delivery should be done in the shortest time. Team-work of technical employees of «CHETA» and YAMAL LNG companies enabled to supply substation within 45 days. Erection and commissioning works were carried out by «CHETA» staff.

 
JSC «Salym Petroleum Development N.V.» PDF Print E-mail

(Zapadno Salymskoe field, Verkhne-Salymskoe field, Vadelipskoe field).

Scope of delivery: Complete power transformer substations 2KTPNU– 2500 kVA, 2KTPNU– 1000 kVA, 2KTPNU – 1250 kVA, 2KTPNU – 1250/35/0.4kV, Closed Switchgear in Block Modular Building ZRU– 35kV, Relay Protection and Automation panels, block-boxes with MCC.

Equipment information: In 2006 «CHETA» LLC supplied substation of voltage class 35/0.4 kV, 6/0.4 kV in in block-modular buildings based on “Schneider Electric” equipment. Due to customer request in substation for voltage 35/0.4 kV were used withdrawable vacuum circuit breakers VD4 of ABB production and the substation for voltage class 6/0.4 kV have been produced based on SM6/RM6 panels. Erection and commissioning works were not applied because of Salym Petroleum Development N.V. staff were trained for such works at erection and commissioning works on earlier shipped substations (shipments from 2007 till 2015).

 
«NOVATEK-PUROVSKY ZPK» LLC PDF Print E-mail

(Purovsky recycling plant of gas condensate the first, the second and the third stages).

Scope of delivery: Complete power transformer substations 2KTPNU–400 kVA, 2KTPNU–630kVA, 2KTPA–2500kVA, 2KTPA –630 kVA, 2KTPNU–400kVA, 2KTPP - 630kVa, 2KTPP–1000kVa, 2KTPP–1600kVa, 2KTPP–3150kVa, MCC’s based on a withdrawable unit.

Equipment information delivery: Cooperation of Novatek- Purovsky ZPK LLC and «CHETA» LLC has been beginning since 2004 and proceeds till now. Deliveries, installation and operational commissioning of 2PTS were executed in 2004 at the first stage of Purovsky construction. In 2008 at the second stage of Purovsky ZPK construction, «CHETA» LLC executed the delivery of control centers 0.4kV, switchgears 0.4kV and PTS 2x1000kVA-2x3150kVA. In 2012 and 2013, «CHETA» LLC had productive manufacturing and delivering experience of the equipment for NOVATEK-Purovsky ZPK LLC at the third stage of construction. The following deliveries of PTS were executed: Complete power transformer substations 2KTPA-2500C-10/0.4-UZ-2 units, 2KTPNU - 400C-10/0.4-UZ-1unit, 2KTPP - 630C-10/0.4-UZ-1 unit, 2KTPP - 630C-10/0.4-UZ-1 unit, 2KTPP - 1000C-0/0.4-UZ-1 unit. During active interactions between «CHETA»’s technical specialists and customer’s specialists have succeeded to make changes to the project, which allowed optimizing the project’s costs. And the possibility of the operational solutions of questions allowed reducing the terms of installation and operational commissioning of the equipment.

 
Russian (CIS)English (United Kingdom)



 

Reference list

Here you may familiarize yourself with our reference list

 

GE product catalogue

CHETA, Llc is official distributor of GE Consumer & Industrial in Russia

GE Intelligent Platforms

Siemens automation

Rockwell Automation

Phoenix Contact

Rittal

Schneider Electric

Circutor

KPB Intra


ja_mageia

  • Наверх